Boiler Layup Procedures
Weekend
Shutdown and Wet Storage
Boiler Wet Storage
The function of chemicals used in wet layup is to control
corrosion by keeping the water oxygen free, to passivate metal surfaces, and to
adjust the pH of the water.
The chemicals used for this purpose may be nonvolatile or
volatile.
Only volatile chemicals should be used for laying up units
with superheaters and reheaters to avoid formation of objectionable deposits in
these locations when operation is resumed.
The specific chemicals usually used and the concentrations
at which they should be maintained in the layup water are shown as follows:
Chemical (nonvolatile)
|
Control Limits
|
BL 1285
|
200 ppm minimum as
|
BL 1513
|
50 ppm or as needed to adjust
pH 10.0 minimum
|
Note : If BL 117+, use 200 ppm, maintain min. 1 ppm N2H4
If B 120+, use 150 ppm, maintain min. 75 ppm SO3
There are differences of opinion on whether catalyzed
oxygen scavengers have advantages over the uncatalyzed type. Regardless of
whether an uncatalyzed or catalyzed oxygen scavenger is used, the recommended
concentration should be maintained in the boiler water. The oxygen scavenger
used for boiler water treatment is suitable for boiler layup.
Recently there has been considerable concern over the use
of hydrazine as a water-treating chemical because of its being a suspected
carcinogen. OSHA regulations specify that an operator should not be exposed to
air containing more than 1 ppm of hydrazine as N2H4.
Adequate safety precautions must be observed in the handling of hydrazine in
order to prevent body contact. Tests have been run for hydrazine in air in
operator handling areas and results have shown hydrazine concentrations far
below the mg/l (ppm) maximum specified by OSHA. Nevertheless, adequate handling
precautions must still be observed.
Closed feeding equipment is available for handling
hydrazine so that operator handling and exposure are practically eliminated.
Before a boiler or auxiliary equipment laid up with hydrazine-treated water is
entered by personnel after draining, the boiler must be flushed with the best
quality water available to remove any residual hydrazine. This procedure should
reduce the concentration of hydrazine in the air well below the 1 ppm
concentration specified by OSHA. Volatile nonhydrazine chemicals have been
proposed as substitutes, but field experience with these chemicals is not as
extensive as with hydrazine.
For wet layup, an empty boiler is completely filled with
water containing the recommended concentrations of layup chemicals. Only
volatile chemicals should be mixed with water used to lay up superheaters and
reheaters. After a boiler is filled and sealed, a slight pressure should be
maintained to prevent air inleakage. This can be accomplished by pressurizing
to 5 psig (34 kPa) with nitrogen, or by connecting a head tank filled with
treated layup water to the highest vent on the boiler.
An alternate wet layup procedure is to connect the
continuous blowdown line from an operating boiler to a convenient bottom
location of a laid up boiler, and to pipe the overflowing water from a steam
drum vent to an adequate disposal location. When this procedure is used, the
blowdown water from the operating boiler must be essentially free of suspended
matter.
Regardless of the wet layup procedure used, the fire/gas
side of a boiler must be free of deposits, dry, and kept dry during the layup
in order to prevent corrosion damage.
¨
One hour prior to scheduled
shutdown, raise the pH of the condensed, saturated steam to 9.5 by increasing
the feed rate of BL-1513 (5% maximum).
¨
Follow normal takedown procedures
by closing the nonreturn valves and drains. Close the continuous and bottom
blowdown valves and open the drum vents.
¨
While the boiler is cooling and
when pressures drop below 50 psig, open superheater drains to remove condensate
buildup. Repeat every four hours until all condensate is removed.
¨
Install a nitrogen bottle with a
pressure regulator/indicator to each boiler steam drum vent and pressurize the
boiler to 2 psig.
¨
When all boilers are below 2 psig
and the nitrogen blanket of 2 psig has been applied, open the superheater vents
for a period of one hour to insure air purge. Close all vents after one hour.
¨
Begin circulating pumps (if
available) and injecting BL-1285.
¨
After the BL-1285 has been added
to all recirculating boiler waters, wait two hours before testing these waters.
DEHA residuals should be 100 ppb minimum, with pH at 10.5 minimum.
If the HRSG is to be returned to service
without draining and volatile chemicals have been used in the high-pressure
boiler, DEHA should be 500 ppb minimum, with pH at 10.0 minimum.
Boiler Dry Storage
Boilers that are out of service are vulnerable to corrosion on the
internal surfaces. The procedure that follows is designed to allow boilers to
be kept off line for any period of time without damage. Regardless of the
method employed, the boiler should be thoroughly cleaned and inspected prior to
storage.
Dry layup is generally used in boilers that will be out of service for
long periods of time or that are subject to freezing.
¨
The boiler should be thoroughly
dried by circulating warm or hot air. This can be accomplished by stoves or, in
some units, a small wood fire. Special attention is required for nondrainable
superheaters.
¨
A chemical desiccant is placed in
each drum so that air circulation below the container is possible. The more
commonly used materials are quick lime (8–10 pounds per 1,000 pounds/hour rated
capacity) or silica gel (10–12 pounds per 1,000 gallons of boiler holding
capacity, or 8–10 pounds per 100 ft3 of air space).
¨
As soon as the desiccant is in
place, close all boiler openings and tightly blank all connections.
¨
An inspection of the desiccant and
an evaluation of its continued ability to absorb moisture should be made every
two to three months.
thk informasinya
BalasHapus